What a Modular Woodwork Quotation Must Say, Line by Line

A quotation you cannot compare is not a quotation, it is a number. Four lines decide whether you can hold a firm to what it promised: board, finish, hardware and edge banding, each named rather than described. Everything else in a woodwork quote is detail; those four are the specification.

Which Four Lines Actually Matter?

These are the ones where a vague line and a precise line produce visibly different furniture at the same headline price.

LineA vague versionWhat it should say
Board"Good quality ply"Brand, grade, IS standard, thickness, and which element it is used for
Finish"Premium laminate"Brand, decor code, thickness, and whether both faces are finished
Hardware"Branded hardware" or just "Hettich"Brand, model or range name, load rating, and quantity per unit
Edge banding"Edge banded"Thickness, and explicitly that all four edges are banded including hidden ones

A brand name alone is the most common gap. Every major hardware manufacturer sells ranges at very different performance points, so "Hettich" could mean almost anything. The model is the specification; the brand is the family it belongs to.

What Does a Vague Line Actually Cost You?

The ability to tell whether you got what you paid for, and the ability to compare one firm against another.

Consider two quotations with the same total. One says "BWP ply, branded hardware, premium laminate". The other names the board brand and IS 710, the hinge model with its load rating, and the laminate decor code and thickness. These describe potentially very different furniture, and only the second can be checked against what arrives on site.

It also costs you later. When a hinge fails in year four, a quotation naming the model lets you buy the same one. A quotation saying "branded hardware" leaves you guessing, and a replacement that is close but not identical is how a run of doors ends up feeling inconsistent.

What Should a Renovation Quotation Show That a New One Does Not?

What is being kept. This is the single biggest difference and the one most often missing.

In a renovation the value is as much in what stays as in what is supplied. A quotation that lists only the new items tells you what you are buying but not what you are saving, and it makes the price look arbitrary.

A renovation quotation should list retained items explicitly at zero: carcass retained, wall fixing retained, loft box retained, internals retained. Seeing those lines is what makes the rest of the number make sense, and it is also a record of what was inspected and judged sound.

It should also state the warranty split plainly, because no firm can warranty a carcass it did not build. Everything supplied and fitted carries a written warranty; the retained structure does not. A quotation that offers blanket cover across both has either not read the job or is not planning to honour it.

Which Exclusions Are Worth Reading Twice?

Exclusions are where the surprises live, and the useful ones are specific rather than general.

  • Civil, wet and electrical work. Ours excludes all of it. If yours does not say, ask
  • Wall preparation. Who corrects a wall that is out of plumb or has loose plaster
  • Making good. Who repairs the wall surface where an old unit was removed
  • Debris removal. Whether it is included and where it goes
  • Society deposit. Normally the owner's, but it should be stated
  • Appliances and sanitaryware. Supply and fitting are different lines
  • Transport and lift charges where a society levies them

None of these is unreasonable to exclude. All of them are unreasonable to leave unstated, because an unstated exclusion is discovered at the worst moment.

How Do You Compare Two Quotations That Look Different?

Normalise before you compare. Two quotations are rarely for the same thing, and the totals mean nothing until they are.

  1. List the units covered in each. Often one includes the loft or the utility and the other does not
  2. Compare board grade per element, not overall. One may specify BWP in the kitchen base and MR elsewhere; the other may use MR throughout
  3. Compare hardware model, not brand
  4. Check edge banding coverage and thickness
  5. Check what is retained versus replaced, if it is a renovation
  6. Read both exclusion lists side by side
  7. Only then compare totals

Most of the time this exercise reveals that the cheaper quotation is cheaper because it is for less work or lesser specification, which is useful to know and is not an accusation against anyone.

What Should You Simply Ask For?

Five requests, all reasonable, and a firm's response to them tells you a great deal before any work starts.

  • The IS standard on the board line, not a description
  • The hardware model number and count per unit
  • The reveal gap in millimetres, so the finished work has a number to meet
  • Retained items listed at zero, on a renovation
  • The warranty split in writing, stating what is covered and what is not

A firm that supplies all five has thought about the job. A firm that cannot supply them does not yet know what it is buying, which means neither do you. That is a more useful signal than anything in a brochure.

Frequently Asked Questions

What should a modular woodwork quotation include?

Four lines decide everything: board with brand, grade, IS standard and thickness per element; finish with brand, decor code and thickness; hardware with brand, model, load rating and quantity; and edge banding with thickness and explicit confirmation that all four edges including hidden ones are banded.

Is "Hettich hardware" a specification?

No. Every major hardware manufacturer sells ranges at very different performance points, so a brand name alone could mean almost anything. The model number and the load rating are the specification; the brand is only the family it belongs to.

What does a vague quotation line cost me?

The ability to check that what arrived matches what you paid for, and the ability to compare two firms. It also costs you later: when a hinge fails in year four, a quotation naming the model lets you buy the same one, while "branded hardware" leaves you guessing.

What should a renovation quotation show that a new-build one does not?

What is being kept. Retained items should be listed explicitly at zero, because in a renovation the value is as much in what stays as in what is supplied. Those lines are also a record of what was inspected and judged sound.

Should a warranty cover retained items?

No honest one can. A firm cannot warranty a carcass it did not build. Everything supplied and fitted should carry a written warranty and the retained structure should not, stated plainly. A quotation offering blanket cover across both has either not read the job or is not planning to honour it.

Which exclusions matter most?

Civil, wet and electrical work; wall preparation; making good where an old unit was removed; debris removal; the society deposit; appliances and sanitaryware; and transport or lift charges. None is unreasonable to exclude. All are unreasonable to leave unstated.

How do I compare two quotations with different totals?

Normalise first. List the units covered in each, compare board grade per element rather than overall, compare hardware model rather than brand, check edge banding coverage, check what is retained, read both exclusion lists side by side, and only then compare totals.

What should I simply ask every firm for?

The IS standard on the board line, the hardware model number and count per unit, the reveal gap in millimetres, retained items listed at zero on a renovation, and the warranty split in writing. A firm that cannot supply these does not yet know what it is buying.

Key Takeaways

  • A quotation you cannot compare is a number, not a quotation.
  • Four lines are the specification: board, finish, hardware, edge banding, each named.
  • A brand name is not a hardware specification. The model and load rating are.
  • A renovation quote must list retained items at zero or the price looks arbitrary.
  • No firm can honestly warranty a carcass it did not build. Expect that split in writing.
  • Unstated exclusions are the ones discovered at the worst moment.
  • Normalise two quotes line by line before comparing totals. Usually one covers less.
  • A firm that cannot give you a model number does not yet know what it is buying.

See how to check the finished work, or wardrobe renovation in Bangalore for a survey and an itemised quotation.

Book a survey

Tell us what you have and what is bothering you. We survey the site, tell you honestly what can be retained, and quote per square foot of the work actually done.

About this guide. This is general guidance for homeowners, not a quotation. Every home differs in size, condition, material quantity and access, and all of those change the work involved. Gunmala Interiors prices per square foot of the work actually done, measured during a site survey, so nothing here should be read as a fixed price, a fixed timeline, or a commitment for your home. Material rates and availability also move over time. For a figure you can rely on, book a survey.